Preliminary work
1. Prepare base grade exceeding the
planned terrace surface by 50 cm on all
sides with a sloping of 4 % and install
drainage in the ground.
2. Make a stable gravel or ballast bed
(frost-safe) with 2 % sloping. Then cover with
fine gravel to level uneven spots.
Sub-structure
3. To begin, click the FIX STEP mounts
at the same height level into all FIX STEP
plates. Then stick a piece of retaining band
onto the centre of each one.
Optional: To increase the structure and to
improve step dampening, click a FIX STEP
comfort pad with the corresponding at-
tachment into the mounts. Then stick a pie-
ce of retaining band onto the centre of the
attachments.
→ Cf. page 13
4. Place the FIX STEP edge plates DUO
at a distance of 4 cm parallel to upright
components and at an axis distance of max.
65 cm. Distribute FIX STEP plates parallel
to these at an axis distance of 50 cm. At the
end of the terrace, place FIX STEP edge
plates DUO again.
→ Cf. floor plan substructure
5. To minimize protruding of the construc-
tion planks, turn the FIX STEP plates.
6. For a terrace length of more than
360 cm, a FIX STEP edge plate must be
placed in the area of the end joint of the
smooth-edged boards.
Max. 50 cm Max. 50 cm
1cm
32 cm
7. Click construction plank (40×60mm)
into the FIX STEP mounts with the grooves
down.
8. For a terrace width of more than
360 cm, the ends of the construction plank
must always be offset to each other. To do
so, connect the ends of the planks with a
FIX STEP connection clip adjusted to
32 cm and screw on to one side. Maintain a
distance of 1 cm between the construction
planks.
→ Cf. floor plan substructure 8
32 cm
15,5 cm1cm
7cm
15
,
5c
m
1
4x35
9. For free expansion, the ends of the
smooth-edged boards and of the construc-
tion planks must be positioned in the same
place.
1cm
6cm6cm
32 cm
In addition, to ensure free expansion the
FIX STEP connection clip must be left open
2 cm wide and 1 cm deep for subsequent
installation of the smooth-edged board in
the area of the screw connection.
13 cm
2cm2cm
10. Then exactly align all construction
planks on the side where installation of the
boards begins.
11. After installing the construction planks,
check the position of the FIX STEP plates
and adjust them if necessary.
12. Place perforated tape below the
construction planks and screw it onto all
construction planks by means of the FIX
STEP connection clip. The perforated tape
is used for bracing the terrace.
→ Cf. 12
I
III
II
M6
x16
4x35
13. To attach the FIX STEP edge clamps,
cut out the construction planks first only on
the side from where the boards are to be
installed, 12 cm away from the edge, 5 mm
deep and 2 mm deep.
→ Cf. 13
After that, the two-part FIX STEP edge
clamp is fitted into this groove and to the
construction plank by means of pliers.
I
5 mm
12 mm
IV
V
II
III
14. To prevent subsequent slipping of the
boards, self-adhesive retaining tape must
always be fastened to the construction
plank that is closed to the centre of the
boards.
→ Cf. 14
Installation of the boards
15. The first board is pressed into the
positioned edge clamps. Keep a distance of
2 cm to upright, fixed components. When
using the optional house connection
profile, first insert the board, then position
it.
→ Cf. 15
16. The connected FIX STEP connection
clips are then set onto the each of the
construction planks, pushed against the
board and engaged by means of pliers.
I II
III
IV
17. If boards are to be fastened at a
distance of about 10mm to the ends of
the construction planks, it is necessary to
insert groove bridges before the connec-
tion clips are mounted.
II
I
18. For open decks, cover caps must be
clipped onto edge and connection clips.
19. After installation of three rows of
boards, the deck should be measured so
that parallel installation is ensured.
Attention: Since the FIX STEP connection
clips are only used to secure the boards in
vertical position, they must be fixed to the
construction planks in every third row of
boards by means of the supplied screws
before they are clipped on. Repeat procedure
until the last but one board is installed.
3
6
20. Then determine the length of the con-
struction planks and saw them off to be
flush.
21. Then create the groove for the edge
clamp and finish installing the boards.
→ Cf. installation step 13
22. Now cut the front end of the boards in
the area of the edge to length with boards
extending 1.5 cm over the construction
planks and bevel the cutting edge.
23. Cut smooth-edged boards to length
parallel to the construction planks; the
smooth-edged board on both ends of the
terrace must be 1.2cm shorter than the
construction plank.
6cm
1,2cm
Hold on smooth-edged board and drill
together with the construction plank using
∅ 7mm drill holes. Keep the maximum
distance of 6cm to the ends and 50cm
between drill holes. Then re-drill smooth-
edged boards with ∅ 10mm, lower and
attach by means of screw, washer and nut
using a distancing groove of 1cm to adjust
to the terrace deck.
1cm
1,5cm
4cm
M8x80
Cut smooth-edged boards
parallel to the substructure and drill
together with the construction plank
with ∅ 7mm. Re-drill smooth-edged
boards with ∅ 10mm and install them.
M8x80
4cm
1cm
18
.
F
clippe
19.
A
board
that p
Atten
clips a
vertic
const
bo
ar
d
before
until t
20.
T
struc
flush.
21.
T
clamp
→ Cf.
22.
N
the ar
exten
plank
15
OFFENES DECK
14
13
12
15
2
1
4 %
2 %
Sloping in
installation direction
MOUNTED INSTALLATION
10,4 cm
Max. 65 cm
Max. 50 cm
Keep the minimum distance of
4 cm to upright, fi xed components.
Ventilation
from below
Water draining
for drainage system
Hint:
The FIX STEP system does not create
the sloping of the terrace.
Hint:
WAVE barefoot boards (open) require
increased care and cleaning e orts – it is
necessary to remove dirt from the grooves
in the boards regularly. The distance
between the axes of the construction
planks is 40 cm. A minimum sloping of
2% in longitudinal direction is absolutely
necessary.
4 cm
distance from edge
plate DUO to fi xed
components
Max. 50 cm
distance between
the axes of all
plates in installation
direction of the
boards
Distance between axes
of all plates in installation
direction
Max. 65 cm
Set connection clip crosswise in the
centre between plates
FIX STEP SYSTEM
OPEN DECK
2 cm
GROUND LEVEL INSTALLATION
Hint: Ground level installation
To ensure the required ventilation from
below, ground level installation is only
permitted as open deck. A distance
of 2 cm to upright, fi xed components
must always be kept.
8
Floor plan substructure
4 cm
14
Attention:
Since the FIX STEP connection clips are only
used to secure the boards in vertical position,
they must be fixed to the construction planks
in every third row of boards by means of the
supplied screws before they are clipped on.